Peerless Fence (“A Division of Peerless Enterprises, Inc.”), St. Charles, IL, is a fence contractor that submitted two proposals to the HOA through Association Partners, Inc. (attn: Marjorie Comber) in late summer 2026: a repair of the HOA-owned Rt. 59 fence and a replacement of the HOA-owned split-rail fence at the pond/wetland. The Rt. 59 repair proposal was accepted: the contract ($1,980) was signed by Board President Mike Coker on September 18, 2026 and delivered to Peerless by API on September 21, 2026 (handled by email, before the October 1 meeting; per user, October 2026). The Board formally approved the $1,980 on October 1, 2026 (EB motion, MH second). The split-rail proposal was not covered by that contract and was not selected — the Board chose Classic Fence ($6,390) for the split-rail on October 1, 2026. It is distinct from first-class-fence, the vendor used for the 2019–2020 Rt. 59 replacement and the 2024 repair.

Proposals (October 2026 packet)

DateJobScopePriceStatus
2026-08-04Repair Cedar Shadowbox Fence (Rt. 59)Remove 2 panels, 1 steel post and footing; install about 15 LF of 6’ cedar shadowbox (1”x6”x6’ flat-top pickets alternating sides, three 2x4x8 stringers per section, galvanized PostMaster post in 36” concrete); haul away excess soil$1,980Accepted — signed 9/18/2026 (M. Coker), delivered 9/21/2026 via API; Board approved 10/1/2026 (EB/MH). 50% down (about $990) at order, balance on completion. Work completion not yet recorded
2026-09-28Replace 2-Rail Fence (split rail)Remove 260 LF of 2-rail split rail; supply and install 260 LF of 2-rail fence; posts tamped in existing soil$4,730 (treated pine, “Old English” style) or $7,230 (Western red cedar)Not selected (Board chose classic-fence on 10/1/2026); manager’s report says the rep states the pine will last longer

Terms common to both: Peerless submits the building permit application and the Association pays the fees; exclusions are permits, bonds, licenses, fees, landscape restoration and marking of private utilities; proposals may be withdrawn if not accepted within 30 days; 1.5% per month on unpaid balances.

Contact Information

  • Address: 200 W. River Dr., St. Charles, IL 60174
  • Phone: (630) 877-2720 / (630) 584-7710
  • Proposals signed by Michael R. Newman, Sales and Estimating

fence-regulations, vendor-contracts, reserve-study-findings

Meeting History

DateEvent
2026-08-04Proposal for the Rt. 59 repair ($1,980) issued. Source: board-packet-2026-10-01
2026-09-18Rt. 59 repair contract ($1,980) signed by Board President Mike Coker. Source: user-reported (email approval); proposal copy in board-packet-2026-10-01
2026-09-21Signed contract delivered to Peerless by API (Marjorie Comber). Source: user-reported
2026-09-28Proposal for split-rail replacement ($4,730 pine / $7,230 cedar) issued; competes with classic-fence ($6,390). Source: board-packet-2026-10-01
2026-10-01Rt. 59 repair contract (already signed 9/18) placed on the agenda for Board ratification (agenda item 8a); split-rail replacement for discussion/approval (8b). Outcome (October 1 minutes): the $1,980 repair was approved (EB motion, MH second); the split-rail bids from Peerless ($4,730 pine / $7,230 cedar) were not chosen — the Board approved Classic Fence at $6,390 instead. EB will salvage undamaged pickets from the damaged section for missing pickets elsewhere on the Rt. 59 fence. Source: minutes-2026-10-01, board-packet-2026-10-01